Draw Network diagram calculator
Home
>
Operation Research calculators
>
Network diagram calculator
Algorithm and examples
PERT and CPM
Draw Network diagram
Type your data, for seperator you can use space or tab
for sample click random button
OR
Rows :
Click On Generate
Indirect Cost =
Month / Week =
Indirect Cost =
- 1-22-32-43-43-64-55-66-77-8
Solution
Help
Solution
Solution provided by AtoZmath.com
Solution provided by AtoZmath.com
Draw Network diagram calculator
1. An assembly is to be made from two parts X and Y. Both parts must be turned on a lathe
Y must be polished where as X need not be polished. The sequence of acitivities, together with their
predecessors, is given below
Activity
Description
Predecessor Activity
A
Open work order
–
B
Get material for X
A
C
Get material for Y
A
D
Turn X on lathe
B
E
Turn Y on lathe
B,C
F
Polish Y
E
G
Assemble X and Y
D,F
H
Pack
G
Draw a network diagram of activities for the project.
2. Listed in the table are the activities and sequencing necessary for a maintenance job on
heat exchangers in a refinery
Activity
Description
Predecessor Activity
A
Dismantle pipe connections
–
B
Dismantle heater, closure and floating front
A
C
Remove tube bundle
B
D
Clean bolts
B
E
Clean heater and floating head front
B
F
Clean tube bundle
C
G
Clean shell
C
H
Replace tube bundle
F,G
I
Prepare shell pressure test
D,E,H
J
Prepare tube pressure test and reassemble
I
Draw a network diagram of activities for the project.
3. Listed in the table are the activities and sequencing necessary for the competion of a
recruitment procedure for management trainees in a firm.
Activity
Description
Predecessor Activity
A
–
B
A
C
A
D
C
E
B
F
C
G
D,E
H
G
I
H
J
F
K
I,J
L
K
M
L
N
J
O
M,N
Draw a network diagram of activities for the project.
4. An established company has decided to add a new product to its line. It will buy the
product from a manufacturing concern, package it, and sell it to a number of distributors that have been
selected on a geographical basis. Market research has already indicated the volume expected and the size
of sales force required. The steps shown in the following table are to be planned.
Activity
Description
Predecessor Activity
Duration (days)
A
Organize sales office
–
6
B
Hire salesman
A
4
C
Train salesman
B
7
D
Select advertising agency
A
2
E
Plan advertising campaign
D
4
F
Conduct advertising campaign
E
10
G
Design package
–
2
H
Setup packaging campaign
G
10
I
Package initial stocks
J,H
6
J
Order stock from manufacturer
–
13
K
Select distributors
A
9
L
Sell to distributors
C,K
3
M
Ship stocks to distributors
I,L
5
(a) Draw an arrow diagram for the project.
(b) Indicate the criticla path.
(c) For each non-critical activity, find the total and free float.
5. An established company has decided to add a new product to its line. It will buy the
product from a manufacturing concern, package it, and sell it to a number of distributors that have been
selected on a geographical basis. Market research has already indicated the volume expected and the size
of sales force required. The steps shown in the following table are to be planned.
Activity
Description
Predecessor Activity
Duration (days)
A
–
14
B
A
4
C
B
2
D
C
1
E
A
2
F
E
3
G
E
2
H
E
4
I
H,L
3
J
K
12
K
D,F,G
4
L
J
2
M
H,L
2
(a) Draw an arrow diagram for the project.
(b) Indicate the criticla path.
(c) For each non-critical activity, find the total and free float.